Thursday, September 14, 2006

Family Care Center Update






Work continues at the Family Care Center. The two four bedroom apartments are dried in and tile is being installed in the bathrooms. They are located on the second floor of the garage wing. On the first floor of that wing the garage door has been moved to the other side of the building giving us a nice interior courtyard and a great exterior entrance to the garage. The first floor apartment will be five bedrooms and two baths and the bedrooms are being framed out currently.
Most of the focus currently is on the exterior boiler room which will house the heating tanks for both hot water and the heating system. In the other wing lots of brick laying and window installation is going on currently. We are in the last two months of warm weather and have to get some projects completed before winter sets in. Igor and crew are making great progress in that direction.

No comments:

 This blog is being used as our archive for our ministry previous to 2020. For current information about our ministry please visit our websi...